Demolition permit

Please note in particular our information under:
  • Performance specification

    The removal of installations, including structural installations, is also subject to the regulations of the State Building Code, among others.

    A demolition permit is required for

    • Buildings with more than 300m3 gross volume,
    • Buildings used for agriculture, forestry or horticulture with a gross floor area of more than 150 m² and
    • Container over 150 m³ container capacity

    regularly required. Independently of this, the stability of neighbouring buildings must be checked by the building owner if they are built together or if the building ground gives cause for this.

    If approval, permission or consent is required for the removal of the installation according to other regulations, this must be obtained before the removal is started. This depends on the individual case, e.g. according to monument protection, nature conservation or waste law or according to conservation statutes of the municipalities.

  • Requirements

    Demolitions requiring approval are examined in the full procedure according to § 66 HBO. In addition to the contents usually to be examined in this procedure, the focus is on the examination of the demolition and disposal concepts.

    In addition to the building permit, other permits may also be required for your building project. These could be, for example:

    • Tree felling permit
    • Notification under water law for handling substances hazardous to water
    • Permit under water law for groundwater contact
  • Which documents are required?

    Special information for - District of Waldeck-Frankenberg

    The following list is intended to serve as a guide as to which building documents must be submitted with a demolition application. You will find out whether these building documents must also be submitted in your specific individual case during the consultation and application acceptance process at the responsible building supervisory authority.

    Type of construction document (in brackets: number):

    1. Application form (1)
    2. Statistical exit survey form (1)
    3. Copy of the extract from the commercial register/register of associations/shareholders' agreement (1)
    4. Powers of attorney in the original (1)
    5. General plan (4)
    6. Property plan (4)
    7. Extract from the parcel/owner record (4)
    8. Open space plan with trees and, if necessary, logistics concept (large demolitions) (4)
    9. Concept for avoiding construction noise in the event of increased construction noise (4)
    10. Floor plans (4)
    11. Cuts (4)
    12. Views, if applicable, photographs (4)
    13. Informal demolition description with demolition and disposal concept (4)
    14. Proof of compliance with the conservation objectives of the conservation statutes (4)
    15. Calculation of the gross volume (1)
    16. Soil expertise or remediation notice (copy) in the case of identified contaminated and suspected contaminated sites (4)
    17. Checklist for the preliminary assessment under species and biotope protection law according to §§ 18, 44 BNatSchG
      or declaration on the information sheet on the consideration of species protection of the LKWaFkb (1)

    Forms can also be found on the homepage of the Hessian Ministry for Economic Affairs, Energy, Transport and Regional Development

  • What are the fees?

    The fee is charged in accordance with the Administrative Cost Regulations for the Business Division of the Ministry of Economic Affairs, Energy, Transport and Regional Development (VwKostO-MWEVL), unless the competent lower building supervisory authority has its own building supervisory fee statutes. The amount of the fee depends on various factors. Information can be obtained from the competent lower building supervisory authority in individual cases.

  • What deadlines do I have to observe?

    The building inspectorate must be notified in writing of the start of demolition at least one week in advance. The completion of the demolition shall be notified to the building supervision at least 2 weeks in advance, stating the time of completion.

    Please use the forms below from the new Building Documents Decree for this purpose.

    The demolition permit becomes invalid if demolition is not started within 3 years after it has been granted or if demolition has been interrupted for one year.

    The demolition permit can be extended on application for up to 2 years at a time. This application can be made informally to the building inspectorate, stating the file number.

  • Processing time

    The envisaged approval period in the full procedure is a maximum of 3 months. However, a fiction of the demolition permit after expiry of the deadline is not regulated by law.

  • Legal basis

  • What else should I know?

    The demolition of buildings without planning permission must also be carried out by a specialist company. The regulations under nature conservation and monument protection law as well as the applicable preservation statutes must be observed.