Notice of commencement of construction

  • Performance specification

    The building owner must notify the building supervisory authority in writing at least one week in advance of the commencement of work on projects requiring approval (notice of commencement of construction).

    Closes the project

    • Combustion plants,
    • Combined heat and power plants,
    • Combustion engine driven heat pumps and
    • Fire-heated sorption heat pumps

    including systems for the removal of waste gases, the expert for energy generation systems must also be notified of the start of construction.

    No notification is required if your building project does not require a building permit.

  • Which documents are required?

    Notification of the start of construction (see applications/forms)

    With the notification of the start of construction, the certificates according to § 68 HBO must be submitted, if not already done, and the person in charge of the construction management must be named.

  • What are the fees?

    None

  • What deadlines do I have to observe?

    The building supervisory authority must be notified of the start of construction at least one week in advance.

  • Legal basis


Who do I need to contact?

Contact

  • the lower building supervisory authority (building supervisory authorities of the districts, the independent cities and the special state cities) or
  • the expert for energy generation plants; this is the locally responsible authorised district chimney sweep.