Apply for a building permit for the erection of a plant under the simplified procedure

Please note in particular our information under:
  • Performance specification

    The simplified procedure applies to all building projects that are not special buildings, do not require planning permission and are not subject to an exemption from authorisation.

    In the case of building projects that are subject to authorisation exemption, the municipality can declare that a simplified building permit procedure should be carried out. In the case of exemptions, the lower building supervisory authority. The client can also request that the simplified building authorisation procedure be carried out.

    In contrast to the full procedure, the scope of review by the building supervisory authority is significantly reduced in the simplified building permit procedure.

    The subject of the audit is

    • the compatibility of the project with building planning law
    • Deviations, exceptions or exemptions applied for
    • Other provisions of public law insofar as a decision according to these provisions is omitted or replaced due to the building permit.

    The building owner is responsible for ensuring that public-law regulations that are not examined in the simplified building permit procedure are also complied with. In individual cases, a deviation, exception or exemption from public-law regulations that are not to be examined must be applied for additionally. In the event of a violation of these regulations, the building permit authority may stop the construction or demolish what has already been built.

    The building permit expires if you do not start construction work within 5 years of the permit being granted or if construction work has been interrupted for more than 2 years after this period.

    Special information for - District of Waldeck-Frankenberg

    In the district of Waldeck-Frankenberg, the deadline can be extended by up to 2 years in each case with a written application.

  • Process flow

    • You fill out the application digitally in the building portal or in analogue form and submit it together with the required documents to the responsible building supervisory authority.
    • The building supervisory authority will check your application and the documents.
    • If all requirements are met, authorisation is granted.
  • Which documents are required?

    Special information for - District of Waldeck-Frankenberg
    • Application for building permission in the simplified procedure
    • other construction documents, which are usually:
      • Site plan
      • Construction drawings
    • The structural engineering verifications shall be submitted to the building inspectorate prior to the execution of the respective construction phases, and the construction documents not subject to inspection shall be submitted to the building inspectorate prior to the start of construction.
    • Survey form for statistics on construction activity in building construction (building permit/building surplus/construction completion or retirement/demolition/change of use)

    As a rule, you must submit four copies of the building documents to the building supervisory authority of the Waldeck-Frankenberg district, Building Department.

  • What are the fees?

    The amount of the fees is based on the structural costs of the building. The respective local authorities can set fees that deviate from the list of fees in the administrative cost regulations by means of bylaws. Please contact the building supervisory authority responsible for you.

  • Legal basis

  • Applications / Forms