Construction site order for work sites on roads
Performance specification
The contractor must already check which traffic safety measures are necessary and appropriate during the planning phase of the work site based on the local conditions. A written application must then be submitted to the traffic authority for the traffic safety measures to be ordered.
The traffic authority examines the application and the documents submitted and consults the authorities to be involved (police and road construction authority). If necessary, a site inspection is carried out with all parties involved in order to coordinate the necessary measures on site. The necessary measures are then ordered by the traffic authority to be carried out by the contractor.
Process flow
The contractor must check which traffic safety measures are necessary and appropriate during the planning phase of the work site based on the local conditions. A written application must then be submitted to the traffic authority for the traffic safety measures to be ordered.
The traffic authority examines the application and the documents submitted and consults the authorities to be involved (police and road construction authority). If necessary, a site inspection is carried out with all parties involved in order to coordinate the necessary measures on site. The necessary measures are then ordered by the traffic authority to be carried out by the contractor.Requirements
Which traffic measures are required to make the work site safe must always be checked on a case-by-case basis. The contractor and the road traffic authority have access to the guidelines for securing road works (RSA) as well as standard plans for all possible safety measures.
Those responsible for traffic safety and the operation and troubleshooting of any signalling systems must provide evidence of the necessary specialist knowledge in accordance with the information sheet on the general conditions for the specialist knowledge required for traffic safety at road works (MVAS). The ordering authority may authorise exceptions to this rule for work with a minor impact on traffic.
Which documents are required?
- written request
- Proof of the required expertise in accordance with the leaflet on general conditions for the expertise required for traffic safety at road works (MVAS)
- Traffic sign plan (either RSA rule plan or individual)
- possibly diversions plan
What are the fees?
Special information for - District of Waldeck-FrankenbergThe administrative fee is charged in accordance with the Fee Regulations for Road Traffic Measures (GebOSt).
The amount of the fee depends on numerous different factors.
Information in individual cases is provided by the locally competent authority.What deadlines do I have to observe?
Before the start of construction work.
Application deadline: 2 weeks
Legal basis
Typing
2/3
Who do I need to contact?
The road traffic authorities are responsible for issuing the order. These are
- for federal, state, district and municipal roads (all roads with the exception of motorways) in cities and municipalities belonging to districts with more than 50,000 inhabitants, the mayors,
- for state, district and municipal roads in municipalities with more than 7,500 inhabitants and for district and municipal roads in municipalities with up to 7,500 inhabitants the mayors
- and for the rest (federal roads in the territory of district municipalities with up to 50,000 inhabitants and state roads in the territory of municipalities with up to 7,500 inhabitants), the district councils.
- Road traffic authority for the motorways in Hesse is the Autobahn GmbH des Bundes (AdB)